Water authority awards contract

Italian company to excavate 3-mile-long tunnel under lake

It is the largest construction contract ever awarded by the Southern Nevada Water Authority, and fulfilling it won't be easy.

To complete the $447 million job, the Italy-based Impregilo group has to design and excavate an almost 3-mile-long tunnel beneath the bed of Lake Mead to keep water flowing to Las Vegas even if the reservoir drops another 120 feet.

Newsvine Digg Fark Technorati reddit StumbleUpon del.icio.us Slashdot Propeller Mixx Furl Twitter MySpace Facebook Google Bookmarks Yahoo! Bookmarks Windows Live Favorites Ask MyStuff myAOL Favorites

Most Popular Stories
  • NORM: Penthouse wants piece of the Strip
  • RAMPAGE ENDS IN SUICIDE: Man runs amok in Las Vegas
  • ROBBERY-HOMICIDE CASE: Juror sent flirtatious messages
  • Father mourns his daughter
  • NORM: 'Joe the Plumber' too booked for LV
  • Judge asks court to release son arrested after crash that killed girl
  • NORM: Strip club owners, 'Vinny' part ways
  • Police ask: Are there others?
  • Anger over cuts reaches fever pitch
  • Working beneath Lake Las Vegas



  • Water authority board members awarded the contract to Impregilo on Thursday.

    Preliminary work on the tunneling portion of the so-called third straw could begin in as little as a month.

    The project, expected to go on line by 2013, also includes a new pumping station inside Lake Mead's Saddle Island and pipelines linking the third straw to the valley's two existing water intakes and treatment plants.

    Separate contracts for the pumping station and connector pipes are scheduled to be awarded later this year.

    According to an estimate produced in 2007, the entire project could end up costing $817 million.

    Marc Jensen, director of engineering for the authority, said the contract awarded to Impregilo is the largest in agency history and could stay that for a while.

    Starting in 2010, the authority hopes to begin construction of a massive pipeline network to tap groundwater across eastern Nevada. That project is expected to cost between $2 billion and $3.5 billion, but the work probably will be divided up into a number of separate contracts, none of them as large as Impregilo's, Jensen said.

    The company will have to work hard for its money. Excavating the 20-foot-tall, concrete-lined shaft is expected to be difficult, dangerous work. Even 75 feet below the lake bed, workers on the project could get wet.

    "There will be water in-flow. The question is, 'How much?' " Jensen said.

    Using core samples collected from floating drill rigs, authority officials have charted a corridor for the intake shaft that appears to avoid the sort of fractured, volcanic rock that is difficult to tunnel through.

    "That will save money, save time and save the risk of a problem during construction," Jensen said.

    The new intake will draw water from one of the deepest points in Boulder Basin, about four miles from a new treated wastewater outflow that is being built to release the Las Vegas Valley's treated effluent at the bottom of the lake.

    Several authority board members asked about the proximity of the two projects. Kay Brothers, deputy general manager for the authority, said the authority collaborated with the Clean Water Coalition to choose the best locations for the treated sewage outflow and the drinking water intake.

    Impregilo won the tunneling contract over a consortium that included one of the companies now involved in the construction of the Hoover Dam bypass bridge.

    But the losing bidder won't go away completely empty-handed. To compensate the consortium for the work that went into its final bid proposal of $588 million, the authority will pay the group $600,000.

    Jensen said the authority offered proposal payment as incentive to get contractors to bid on the project.

    "They spent more than 600,000 (dollars) preparing their final proposal," he said.



    Leave Your Comment 3 Reader Comments
    Terms & Conditions
    The following comments are provided by readers and are the sole responsiblity of the authors. The reviewjournal.com does not review comments before publication nor guarantee their accuracy. By publishing a comment here you agree to abide by the comment policy. If you see a comment that violates the policy, please notify the web editor.

    Some comments may not display immediately due to an automatic filter. These comments will be reviewed within 48 hours. Please do not submit a comment more than once.
    Current Word Count:

    oldlawdawg wrote on March 21, 2008 03:49 PM: I realize corporations often pay investment banking houses that lose out on LBOs for the costs of their buyout proposals, but why do large contractors need and incentive to bid on a $400+ million dollar contract? That is a big contract ro chase after, and any company that cannotr afford to absorb its own bidd costs does not sound financially stable enough to fulfill such a lareg contract. Call me stupid or backwards, but that sounds like nothing short of sweetheart money.


    DJ2 wrote on March 21, 2008 09:04 AM: It sounds to me like this public utility has taken on a life of its'own.


    ths wrote on March 21, 2008 06:57 AM: Here is the old ways of doing business that can change. They gave money to another company for bidding on the project.

    In todays global economy companies are hungry for large contracts and often will bid on jobs on spec. If they don't get the job then they write it off as a spec lose. Pay to bid has pretty much gone away a decade ago in many private areas and the government should do the same.