ROAD WARRIOR: I-15 widening project staying ahead of clock



On time? Ahead of schedule?

Perish the thought and knock on wood.


Most Popular Stories
  • NORM: Details emerge in Jackson probe
  • VICE ENFORCEMENT'S TOP OFFENDERS: Police are taking unprecedented steps to keep prostitution offenders off the Strip
  • NORM: Jackson changes Las Vegas address
  • NORM: When live news shots turn bad
  • NORM: Lance Burton renews contract
  • Michael Jackson's doctor has history of legal, financial woes
  • NORM: Donny Osmond recalls old friend
  • Motorcyclist killed in collision with CAT bus
  • Motorcyclist killed in crash on Blue Diamond
  • Clark County man dies of H1N1 virus




  • Most Las Vegans probably get sore when they think about Nevada Department of Transportation freeway projects. The decade long construction debacle of U.S. Highway 95 is still too touchy a subject.

    But state transportation officials have long held that the $240 million Interstate 15 north widening project would be different because of the method of design and construction.

    It's been more than a year since engineers and designers armed with pencils and erasers began the project.

    Now state officials are saying the three-year project is on time and may well be completed ahead of schedule.

    "I think we're going to beat it (the March 2010 deadline)," Jeff Hale, the project manager for the Transportation Department, told me.

    The more than 170,000 motorists who daily traverse the 51/2 miles of heavily congested interstate are probably hoping Hale is right.

    The project will widen I-15 from six to 10 lanes from the Spaghetti Bowl to Lake Mead Boulevard, and from four and five lanes to eight lanes from Lake Mead to Craig Road. Interchanges also will be reconstructed at D Street, Lake Mead, Cheyenne Avenue and Craig.

    For more than six months, I-15 commuters have been dealing with a number of issues including lower speed limits, longer travel times, lane shifts, lots of cones and fewer lanes. And since July, many commuters have been avoiding the interstate altogether and are clogging surface streets.

    Motorists already have seen a major road shift and lane reduction that began in July to allow workers to construct new northbound bridges at D Street, Bonanza Road and Washington Avenue.

    And the second round of major changes is on the way.

    Hale said the Cheyenne Avenue onramp to southbound I-15 is expected to be opened by Dec. 14, which should relieve pressure on Losee Road.

    But the southbound Cheyenne offramp will be closed around the same time.

    The Washington onramp to I-15 will be closed beginning Nov. 30, which will affect commuters detouring from U.S. Highway 95 and using Washington via Las Vegas Boulevard to get on northbound I-15. Those motorists will have to travel north to Lake Mead or Cheyenne to get on the interstate.

    Also, the Lake Mead interchange will experience similar disruptions now happening on the Craig interchange. The good news is that the Lake Mead interchange will not shut down, unlike the interchanges closer to the Spaghetti Bowl.

    And in mid-February, a second major lane shift will take place with the completion of the northbound lanes. Northbound and southbound traffic will be moved to commute over the northbound lanes, while the southbound bridges at Washington, Bonanza and D Street are reconstructed.

    "We are aiming for three lanes to be open in each direction by August 2009," Hale said.

    It will be another six or seven months before the ramps near the Spaghetti Bowl are open to commuters.

    Hale credits the speed of construction to the "design-build" scheme, which overlaps the designing and building phases of a construction project.

    In the past, the state has relied on the design-bid-build method, which follows the mantra that a project's design must be completed before a construction firm begins work, with time in between to put the contract out to bid.

    The design-build process alone probably saved two years, Hale said.

    Since this is the Transportation Department's first foray into the world of design-build projects, there has been a learning curve, Hale said.

    For instance, designers had hoped that shutting down cross streets such as Washington and Bonanza wouldn't be necessary.

    "We didn't intend on it," Hale said. But the installation of precast girders, which will be the basis for the reconstructed bridges, required the shutdown or a slowdown in construction would occur.

    One negative impact has been that the timing of construction coincided with the height of inflation for construction material. The rising costs of asphalt and fuel prices cost an extra $1.5 million, Hale said. The extra cost is being shared by the contractor and the state, he said.

    Hale said the sacrifices commuters are making are paying off.

    And motorists who routinely use the interstate can readily notice the swiftness of the construction.

    Hale is still amazed at the speed of the project.

    "We're hoping to be done ahead of schedule," Hale said. "Things are moving very fast."

    Knock. Knock. Knock.

    If you have a question, tip or tirade, call the Road Warrior at 387-2904, or e-mail him at roadwarrior@reviewjournal.com or fmccabe@reviewjournal.com. Please include your phone number.

    Newsvine Digg Fark Technorati reddit StumbleUpon del.icio.us Slashdot Propeller Mixx Furl Twitter MySpace Facebook Google Bookmarks Yahoo! Bookmarks Windows Live Favorites Ask MyStuff myAOL Favorites

    Leave Your Comment 4 Reader Comments
    Terms & Conditions
    The following comments are provided by readers and are the sole responsiblity of the authors. The reviewjournal.com does not review comments before publication nor guarantee their accuracy. By publishing a comment here you agree to abide by the comment policy. If you see a comment that violates the policy, please notify the web editor.

    Some comments may not display immediately due to an automatic filter. These comments will be reviewed within 48 hours. Please do not submit a comment more than once.
    Current Word Count:

    Note: Comments made by reporters and editors of the Las Vegas Review-Journal are presented with a yellow background.

    Richard Dickinson wrote on July 02, 2009 07:30 AM: I read where the contract for widening I15 from Blue Diamond to Tropicana has been let. Does this include replacing the Warm Springs bridge? And is there a plan here to install a bridge over I15 at Sunset?


    roadfro wrote on November 09, 2008 11:30 PM: Kudos to NDOT and the contractor for doing the I-15 north project in design-build manner and keeping ahead of schedule. This method seems to work pretty well, and I hear NDOT is looking to do a I-15 project to the south as design-build also. When you don't have to worry too much about right-of-way, design build is a very viable construction method.

    Tom: The narrow lanes near the Santa Fe are separate from the 95 widening project. That was done recently to add an additional lane north of Craig Rd without adding more asphalt (similar to them adding the auxiliary lanes to US 95 in the late 90s before they started the widening project). I don't see the other problems you speak of, except the jolt going over that bridge at Gowan is quite apparent.


    the truth wrote on November 09, 2008 10:02 AM: ROAD WARRIOR: I-15 widening project staying ahead of clock

    Well, It's just another example of Union contractors and workers doing a superior job. Not like that mess up on the beltway in Summerlin-where non-union Meadow Valley is working and forgot to run the electric on the Lake Mead interchange in sun City-that's why it hasn't opened yet people! Union YES on public work projects!


    tom ronson wrote on November 09, 2008 08:55 AM: lets hope this project ends up better than the 95 project did. The off camber sweeping turn south bound at the Rainbow curve, the horribly lumpy overpass just north of Cheyenne (north bound is far worse), the far too narrow lanes on the curve near Santa Fe, the horrific tilt of the SB lanes between Cheyenne and Lake Mead make that road one of the largest jokes ever. I swear a few drunk monkeys could of done better doing that project than whomever bilked the state on that boondoggle.