NOT-SO-QUICK FIXES: Report reveals discrepancies at MGM CityCenter project

Problems surface in analysis of public records



















It is five months until the first tower is set to open at CityCenter, one of the largest private construction projects in U.S. history, but general contractor Perini Building Co. has not yet resolved numerous construction deficiencies cited by inspectors.

Perini's slow approach to fixing the discrepancies makes it difficult to confirm that actual construction work matches building plans sanctioned by the county.


Most Popular Stories
  • Man shot by police identified as local attorney
  • TRAFFIC STOP: Shooting accounts conflict
  • NORM: At time, drug use wasn't suspected
  • One motorcyclist killed, another critically injured in accident
  • NORM: Marie Osmond, manager battling
  • Nurseries fence out day laborers
  • Second person dies after being restrained by police
  • Boy struck, killed by car pulling out of driveway
  • Three children fall from vehicle; mothers arrested
  • REFUSING THEIR OWN MEDICINE: Vaccination policy spurs legal action




  • The Review-Journal has analyzed the discrepancies inspectors have reported to county building officials since construction began on the project in 2006.

    Clark County and MGM Mirage, the project's owner, say every discrepancy will be eliminated before the buildings open for business; but some construction experts say late fixes may be costly, and impractical, to make.

    MGM Mirage spokesman Alan Feldman downplayed the significance of the project's hundreds of unresolved discrepancies.

    "By the time the buildings are open, there will be 100 percent resolution," Feldman said. "I haven't been involved in any project where something like this wasn't going on."

    Lesley Pittman, spokeswoman for Perini Building Co., the general contractor for CityCenter, said the company's work at CityCenter was well within "established building and construction processes."

    It is "factually untrue," she wrote, to suggest that Perini's work on CityCenter "has been done improperly or inconsistent with the County's existing legal and regulatory process."

    Perini's compliance with existing processes isn't the issue. The question is whether it is wise to continue construction at breakneck speed, while construction discrepancies and work done with unapproved plans pile up.

    Some CityCenter properties are scheduled to open later this year. The Vdara, a nongaming resort, has a planned Oct. 1 opening date. The 4,000-room Aria is scheduled to open Dec. 16.

    OFFICIAL EXPRESSED CONCERN

    Discrepancies, or noncompliance reports as they also are referred to by the county, document problems that third-party special inspectors find during construction, such as outdated plans, bad work or work that doesn't match the latest approved plan. If a problem persists or is deemed to be particularly serious, the county has the option of following up an inspector's report with a correction notice.

    There is evidence some county personnel became concerned that up-to-date approved plans were often absent when special inspectors went to check steps of completed work at CityCenter.

    On Feb. 9, a county inspector reacted by issuing a wide-reaching correction notice.

    "Contractor working without Clark County approved plans," Kurt Stone wrote in the notice, which referenced all building permits at the site.

    The choice to let workers build as project designers revise the original plans -- with supporting papers and county approvals sometimes still missing months or years later -- can impact CityCenter's final construction price tag, and even the safety of future employees and guests, experts say.

    But county spokesman Dan Kulin said the county doesn't study discrepancy logs for any given job site to pinpoint trends during construction. The logs do come into play as a job nears completion.

    "Everything needs to be resolved before we issue a certificate of occupancy," Kulin emphasized.

    Without the certificate, no building can open for business.

    HARMON TOWER IS NOT ALONE

    The beleaguered Harmon Hotel leads the pack in percentage of discrepancies -- 69 percent -- that remained unfixed at CityCenter as of Feb. 13, the newspaper's analysis shows.

    The Harmon's height has been almost halved from the original design, after serious construction errors were found in 15 of about 20 completed floors. Negative publicity streamed from the discovery last summer.

    In January, project owners MGM Mirage and Dubai World announced the deletion of Harmon's 200 condo units, portraying the decision to downsize as economically motivated in the present recession.

    Project owners had decided it was cheaper to reduce the building's final height, and do less costly fixes, than to fully correct errors in the 15 floors. The errors had compromised the ability of a full-sized Harmon to withstand sideways forces including wind or earthquake.

    CityCenter's other towers also have hundreds of unresolved discrepancies, county logs show. In contrast to the Harmon's 69 percent unresolved rate, other structures varied in their rates from 40 percent at the low-rise "west podium" to 22 percent at the Vdara.

    Whether rates of unresolved discrepancies this high are the norm at Las Vegas high-rise construction projects is difficult to measure, because the county doesn't keep records on this subject. Kulin said it would be difficult for the county to produce comparable records for already completed projects, showing the status of discrepancies during construction.

    'SHEER MAGNITUDE' QUESTIONED

    Felix Martin, a forensic structural engineer based in Southern California, makes his living analyzing data for and testifying in construction defect lawsuits. Based on his experience, he believes CityCenter's unresolved rate should be no higher than about 10 percent.

    "I'm concerned about the sheer magnitude" of unresolved discrepancies and missing approvals at the CityCenter project, Martin said after he reviewed the spreadsheets in which the Review-Journal dissected the CityCenter logs.

    There is no industry standard for acceptable rates of unresolved discrepancies at a large, complex project such as CityCenter, or for how frequently special inspectors usually cite unapproved documents when they examine a piece of completed work.

    Generally, construction professionals consider logged items as unimportant "fleas on a camel's back," said Martin, the owner of Marcon Forensics.

    But, referring to the Harmon problems -- in which substantial errors persisted as the building rose 15 floors -- Martin said, "If you're building the obvious incorrectly, how can you guarantee the less obvious has been done correctly?"

    MGM Mirage officials contend the unresolved discrepancy rates at CityCenter aren't unusually high.

    "Many of these things are very minor," MGM Mirage spokesman Gordon Absher said in February. "And some are as simple as the engineering review process catching up with what's happening at the site."

    He was talking about the volume of discrepancies then being logged by inspectors.

    Kulin said the county's system for tracking construction discrepancies speaks for itself.

    "It shows that we're keeping track of NCR's (noncompliance reports) that are out there. ... It's up to you as to what you find interesting."

    County officials Phil Rosenquist, Ron Lynn and Greg Franklin were not available to talk during the 10 days in April that the newspaper made repeated requests to interview one of the three. Rosenquist is the assistant county manager over county development services, which Lynn heads. Lynn supervises Franklin, who heads the building division.

    WHAT THE NUMBERS SHOW

    The Review-Journal analysis of CityCenter found two trends:

    • When Perini requested a special inspection, third-party inspectors frequently reported they had to work with either an old plan, an unapproved revision or no plan at all. Inspectors need the latest approved revision when they examine work.

    • After third-party inspectors logged discrepancies, Perini has let a high proportion of them dangle unresolved for long spans of time.

    The Review-Journal undertook its analysis as a way to evaluate numerous complaints it has received from CityCenter workers -- past and present -- who are engineers, inspectors and tradesmen.

    The newspaper tabulated and sorted the discrepancies in the county logs, which consist of report summaries from third-party special inspectors at the project. Inspectors repeatedly cited the lack of approved documents -- drawings, details or plans -- in their daily reports.

    "They're putting this up like you'd put up a (home) garage," is how one angry former field engineer described the lack of official paperwork.

    Laid off from Perini several months ago, the engineer -- like other workers who contacted the newspaper -- declined to be identified in print. Some said they had expressed their concerns to supervisors, but were ignored. All feared they would either lose their jobs, or be blacklisted from future jobs.

    Third-party special inspectors examine only aspects of construction -- involving concrete, masonry or steel -- that either are highly technical or require intensive monitoring. County inspectors handle less technical work, such as electrical, plumbing or heating-cooling installation.

    Examples of inadequate work that third-party inspectors have logged include concrete batches or column splices that didn't test as strong as approved documents call for.

    Most, but not all, of what appear to be serious discrepancies are marked as resolved in logs.

    The newspaper looked at CityCenter logs for the Harmon and Aria hotel towers; the Mandarin and Vdara towers, which have both hotel rooms and residences; and at Veer Towers, which is strictly residential. It also looked at the county's discrepancy logs for the two low-rise portions of CityCenter that will house the casino and employee areas.

    The newspaper scrutinized site activity from 2006 through Feb. 13, which was the day it received its log copies.

    SLOW FIXES DON'T FAZE COUNTY

    County officials don't appear concerned, either, with the slow pace for resolving discrepancies at CityCenter, some of which date back to 2007 and are still open.

    "It's whether it's resolved, not how long" it took to resolve, Kulin said. "It's up to the owner or contractor to determine when and how they will address" discrepancies.

    That contrasts with the experience of forensic engineer Martin, who said most discrepancies at most projects can be closed in two weeks.

    A more complex discrepancy might take several months, according to both Martin and Charles Moore, who is with a financial restructuring firm near Detroit and is familiar with construction management at large job sites.

    Kami Farahmandpour, founder of Building Technology Consultants in Arlington Heights, Ill., said resolution of the discrepancies is a serious matter.

    "One can deduce that some of the discrepancies indicated in the spreadsheet (if left unresolved) may ultimately cause life safety concerns and code violation," he said after reviewing the newspaper's analysis of county data.

    Unresolved discrepancies in the spreadsheet viewed by Farahmandpour include an issue with masonry reinforcement and four instances of unapproved work.

    Some county documents pertaining to CityCenter contradict Kulin's contention that a contractor can choose how long to let discrepancies stay open.

    On July 9, 2008, county inspector Mike Kemper issued two correction notices for discrepancies that were "not being cleared in a timely manner" at the west low-rise building.

    "NCR's need to be addressed within 10 working days to prevent further action," Kemper wrote in both notices, which pertain to different areas at CityCenter.

    The 10-day deadline is not county policy, but came at the inspector's discretion, according to Kulin.

    As of mid-February, the Review-Journal's database showed that 75 percent of unresolved discrepancies at CityCenter's west low-rise building were at least five months old; 74 percent were that old at Vdara; 64 percent at Veer Towers; 59 percent at the project's east low-rise building.

    The Harmon had the lowest rate, 10 percent, for unresolved discrepancies five months or older, perhaps because of recent intensive scrutiny because of the well-publicized construction errors.

    At the project's west low-rise building, 52 instances of column splices with "less than 75 percent bearing" were still open in mid-February. All the discrepancies date back to either May 8 or June 21 of 2007. The phrase refers to a column not measuring up to prescribed strength.

    A sample of other long-standing discrepancies still open on Feb. 13 include: piping in a basement level doesn't match plan (noted at Veer Towers on April 27, 2007); no approved document on file to justify a particular use of epoxy in the foundation (at east low-rise on May 9, 2007); no permit for cabana work (at Harmon on July 16, 2007).

    Nor do the CityCenter logs list any resolution dates for discrepancies that have been closed.

    Omitting closure dates from discrepancy logs is not common practice, said both Martin and Fred Deis, an official with the Portland, Ore., building department.

    RISK OF LAWSUITS

    Discrepancies that go unresolved for long spans of time carry a risk, several interviewed parties said.

    They disagree that all discrepancies can simply be cleared up at the tail end of a project. Older work tagged with an open discrepancy may have been concealed by subsequent layers of work.

    Even the county admits that one risk of that is greater expense to the builder or owner.

    "It could lead to them having to ... rip out and redo the work," Kulin said. "Or they may have to submit revised plans, which certainly carry some sort of cost, additional engineering and that sort of thing."

    There also is a safety risk, should work that was built without approved plans contain an error.

    The harshest example of that in hotel history is the 1981 collapse of suspended walkways in a crowd-filled atrium at the Kansas City Hyatt Regency. The failure, which killed 114 people, was later linked partially to a poorly vetted revision of the plan that was originally approved for the walkways.

    "The bottom line is, speed will kill, whether it's driving or construction," Deis said. "There's a reason ... that inspectors have record sets that are stamped properly," to show which approvals the plans have received.

    Martin's bottom line is that projects with high unresolved rates for logged discrepancies tend to be the sort that end in construction litigation.

    That prospect is sure to sour the stomachs of the principal players at CityCenter. MGM Mirage and Dubai World already are wrestling over terms of their CityCenter partnership.

    Meanwhile Perini Building Co. is embroiled in a federal lawsuit in which investors contend the company misled them on the status of its Las Vegas projects, including CityCenter.

    Contact reporter Joan Whitely at jwhitely @reviewjournal.com or 702-383-0268. Contact reporter Alan Maimon at amaimon @reviewjournal.com or 702-383-0404.

    Only two of seven commissioners comment on construction logs

    By ALAN MAIMON and JOAN WHITELY

    LAS VEGAS REVIEW-JOURNAL

    Two of seven Clark County commissioners, Steve Sisolak and Chris Giunchigliani, took the invitation to comment on the meaning of construction logs for CityCenter, a mammoth site going up on the Strip, which will offer glamorous condo living and expand attractions for tourists.

    County Manager Virginia Valentine declined comment, as did commissioners Tom Collins, Larry Brown, Lawrence Weekly, Susan Brager and Rory Reid.

    The county's construction logs say that actual work in some cases does not match the approved building plans.

    "All these items will have to be resolved. ... If they have to remove a piece of Sheetrock to fix something, then it's their own fault that they didn't fix it earlier. They have to do what they have to do, however they have to do it. I was assured that none of these things are safety or structural issues. I don't want to say they're insignificant or small, because they're issues that need to be resolved before they get a certificate of occupancy."

    steve sisolak, clark county commissioner

    If the county can improve the process by which building inspectors document construction work, Commissioner Chris Giunchigliani said she is willing to do so.

    "We've gotten into this mold, 'It's not the inspector's job,' or, 'It's not the county's responsibility,'" she said. "At some point we have to use common sense as well."

    On the importance of CityCenter coming on line to generate tourism jobs as well as gaming, room, entertainment and sales taxes: "We cannot afford in this community, in the (economic) downturn, to not have this project moving correctly, safely and also opening in a timely manner."

    Chris Giunchigliani, clark county commissioner

    COUNTY PROCESS STEP BY STEP

    START

    1. Project plans go to county. When county approves them, general contractor pulls building permits.

    2. General contractor sends approved plans to fabricators and subcontractors, who do their own "docs" so workers understand what to make/build/install.

    3. Contractor schedules an inspection by third-party special inspectors when it thinks steel, concrete, and masonry is ready to pass.

    4. Third-party special inspector compares work to the approved plan.

    a. Work passes.

    b. Work doesn't pass, so it becomes a discrepancy logged with the county.

    5. County's quality-assurance inspectors spot-check the work of third-party special inspectors.

    If a problem is found, county inspectors can issue a correction notice, notice of violation or stop-work order.

    6. As a new layer, or type, of construction is about to start, contractor must pull more building permits.

    Regular county inspectors (with different training than third-party special inspectors) do inspections of less technical work, such as electrical, plumbing, heating-cooling and framing.

    7. All open discrepancies in the log are closed and the project passes all its inspections.

    8. Project obtains clearances from fire, sanitation and water departments.

    9. County issues a certificate of occupancy, and the building opens for business.

    FINISH

    EXCEPTIONS

    Any time during construction, an unexpected field condition can force revision of an already approved plan.

    Engineer/design teams can informally pass along the correct fixes by phone or e-mail, for workers to immediately execute.

    But the county must formally approve the plan revision, and a copy must go to the site for third-party inspectors to use.

    Las Vegas Review-Journal

    'READ INSTRUCTIONS BEFORE ASSEMBLING'

    Aria Resort & Casino -- 53%
    Harmon Hotel -- 3%
    Mandarin Oriental Las Vegas -- 30%
    Vdara Condo Hotel -- 42%
    Veer Towers -- 19%
    East Podium -- 26%
    West Podium -- 27%

    * The term "unapproved documents" includesunapproved details, unapproved drawings or unapproved plans.

    Newsvine Digg Fark Technorati reddit StumbleUpon del.icio.us Slashdot Propeller Mixx Furl Twitter MySpace Facebook Google Bookmarks Yahoo! Bookmarks Windows Live Favorites Ask MyStuff myAOL Favorites

    Leave Your Comment 27 Reader Comments
    Terms & Conditions
    The following comments are provided by readers and are the sole responsiblity of the authors. The reviewjournal.com does not review comments before publication nor guarantee their accuracy. By publishing a comment here you agree to abide by the comment policy. If you see a comment that violates the policy, please notify the web editor.

    Some comments may not display immediately due to an automatic filter. These comments will be reviewed within 48 hours. Please do not submit a comment more than once.
    Current Word Count:

    Note: Comments made by reporters and editors of the Las Vegas Review-Journal are presented with a yellow background.

    Report abuse

    QA/QC wrote on July 12, 2009 09:28 AM: so who would think that the quality of work is so poor - products from china are being used - the defects are running rapid - there is just to much work to do with a labor force that is just too inexperienced and a contractor that has no idea on how to manage the quality - ask around town about the extensive rework on systems and finishes - there are repairs going on in the tune of tens of millions of dollars - so how can new construction become a renovation - hire the wrong contractor who makes deals behind doors with subs and unions


    Report abuse

    PE wrote on April 27, 2009 05:35 PM: The percentages of open NCRs are surprising given how close they are to complete. It's also surprising that they have so many old unresolved issues given that they are building all the Towers out of structural concrete. Conformance to plans is typically much easier in this type of construction as connection detail improvisations are rarely necessary. Connection details often lead to a lot NCRs when building out of structural steel when shop fit up meets field fit up. I'd be interested to know what the statistics look like for similar size projects such as Fontainebleau?


    Report abuse

    2 Peas in a Pod wrote on April 27, 2009 05:52 AM: I would like to single out tom1 and Not Again! for their unique take on the above article. They are living proof that the Clark County School District should be abolished. Missing the point is one thing. NOT HAVING A CLUE, deserves a response.

    To think for a moment that the City Center debacle is not newsworthy, defies reality. To think that the RJ is somehow trashing MGM in this article is beyond reality.

    When the geniuses at MGM/DUBAI decided to turn the Strip into a Clusterf#ck Condof#ck with a side order of Gridlockf#ck like this Town has never seen, they clearly made a mistake. A $9 BILLION DOLLAR MISTAKE. The condos aren't selling. They're suing each other. DUBAI wants out. Why? MGM is BROKE. They're having a "going out of business" sale. Read the Las Vegas Sun article in today's paper.

    tom1 and Not Again! apparently aren't aware of any of those facts. Obviously they work there. Probably landscaping.

    The RJ staff writer, Joan Whitely, exposes the PURE INCOMPETENCE of the Clark County Building Department, when it comes to monitoring the work being done at this disaster waiting to happen. That's what this story is about. She did the same thing at the Rio. She did the same thing at Harrahs. She is an Investigative Reporter. That's what Joan Whitely does for a living.

    Wouldn't it be nice to be like tom1 and Not Again! and have all the news of the day put through a filter, strained and spoon fed, as to not upset their little tummies? Yummy!

    Maybe when they're done planting their TULIPS on the hind T1T of the MGM lion, they can get that GED and take another whack at reading comprehension.

    Sound it out guys. You're the only ones that don't get it. Wipe your chins. No. Really.



    Report abuse

    Right on the money wrote on April 27, 2009 02:47 AM: In case you missed it

    http://www.latimes.com/news/opinion/la-oe-maher24-2009apr24,0,927819.story


    Report abuse

    President Obama supporter wrote on April 27, 2009 02:37 AM: Conservative whine babies, copy and paste this article in your browser for your reading pleasure. No one likes or for that matter even cares what you think anymore Here you go http://www.latimes.com/news/opinion/la-oe-maher24-2009apr24,0,927819.story


    Report abuse

    Free Nevada wrote on April 27, 2009 01:42 AM: @tom1, MGM-MIRAGE is a for-profit company in business for itself, not for you or me or anyone else in Las Vegas. Without focus of RJ and others, they might get away with erecting unsafe buildings. I mean, it's not like they aren't building a pile of skyscrapers in extremely close proximity, some at steep angles, at the base of an ancient volcano in the Ring of Fire at a time when, based on analyzing millions of years worth of evidence, we are now 100% certain we're at least 30 years overdue for a major earthquake. Please push your boring presidential politics some place else.


    Report abuse

    tom1 wrote on April 27, 2009 12:40 AM: Not Again! - IS ON THE MONEY

    Why don't you dummies at the RJ report on Obama and his tribe, no disrespect intended, but now that your think of it you could call the liberals a tribe, yes a tribe or better yet a gang of thieves.

    Expose how they are destroying what America is about: liberty.

    You people should respect the MGM and all the company has done for Las Vegas. Seek headlines elsewhere...traitors !!!!


    Report abuse

    Grand Opening wrote on April 26, 2009 09:59 PM: I heard that Palm Mortuary is footing the bill for the Fire Works. I'm dying to see how that turns out.


    Report abuse

    Death Traps wrote on April 26, 2009 06:22 PM: Ok now would anyone really want to purchase any condo in these units knowing what this article exposes as defects! Hell no. These are death traps just waiting for the first doofus to be killed when they structurally fail! Would you even want to work in one of these buildings? Ya Right!


    Report abuse

    Bob wrote on April 26, 2009 04:35 PM: Bad Karman property. Similar to the Super Dome built on an old indian cemetary. Dead bodies left and right on this project and they kept building to get the bonus.


    Read All Comments