Railroad cost estimates for Yucca top $3 billion

WASHINGTON -- The cost of building a government railroad across rural Nevada to carry nuclear waste to Yucca Mountain has grown beyond $3 billion and is climbing with groundbreaking still several years away, according to new estimates.

The Department of Energy has set $3.155 billion as the latest price tag to run rail about 319 miles from Caliente in eastern Nevada to the Yucca site in Nye County, about 100 miles northwest of Las Vegas.

Previously, a cost estimate disclosed in December 2005 was $2 billion.

The numbers underscore the growing cost of the proposed Nevada nuclear waste complex, and the likely challenges facing the Energy Department to secure funding from Congress for the undertaking.


Most Popular Stories
  • LANDLORD: AS TENANT, FLEISS FOR THE BIRDS
  • NORM: So, that's why it's titled 'Mindfreak'
  • 1958 CRASH: DEATH IN DESERT AIR
  • CALICO BASIN: Tranquillity lost
  • NORM: Daughters say Barrier left sign
  • NORM: 'Idol' contestant set to go country
  • NORM: Reid book reveals 'Casino' mystery
  • NORM: Jackson in action possibly in Vegas
  • NORM: Cruise the object of a twin crush
  • Durango teacher accused of sex acts with student



  • "I think this is going to be a big pill to swallow on Capitol Hill," said Bob Loux, executive director of the Nevada Agency for Nuclear Projects.

    "This goes to show the longer things get delayed, the more expensive it will be for the rising costs of concrete and steel," Loux said. "But also that this is a more difficult job than they thought before."

    The Energy Department in March estimated that repository construction and transportation, and initial operations at the site, would cost $27 billion. The department has not updated broader and longer range "life cycle" costs, which were at $57.6 billion in 2001.

    The government still is at least several years away from breaking ground for a railroad and for waste-handling buildings beyond the five-mile long wide-mouth exploratory tunnel and study facilities at the site already.

    Project director Ward Sproat, at a meeting Friday with Nevada county officials, said railroad groundbreaking likely will be delayed beyond 2009, according to several meeting participants.

    Sproat told them that he was not sure if the rail project would have the funding to start by then, officials said. DOE has routinely steered money from Yucca transportation segments to complete a license application that is considered to be a more pressing priority.

    A 54-page draft national transportation document containing the new railroad cost estimates was circulated last week among state and local officials, potential repository vendors and other stakeholders.

    DOE spokesman Allen Benson said the new dollar amounts for a Nevada railroad are based on "a better understanding of the cost of facilities, understanding there was a lot more work done on (the plan) and we have had a better look at the costs."

    "As we come closer to construction, we will have to update the costs," Benson said. "This is where we are at this point."

    The rail cost estimates include features such as an equipment yard, maintenance facilities, a train control center and sidings to connect the line to existing track in Caliente, according to the DOE transportation document.

    Bob Halstead, a transportation consultant under contract to the state of Nevada, said DOE's estimate still might be low.

    "Not knowing what went into these numbers but having done detailed cost exercises and having revisited the numbers to adjust them, I would say these DOE numbers seem credible but they still might be too low. The high number could be $3.6 billion or $3.7 billion," Halstead said.

    Halstead also said that as the rail costs continue to grow, DOE might come under pressure from trucking companies to abandon rail and ship nuclear waste to the Yucca site by truck as a more economical choice.

    That scenario would open a host of new controversies, though, as the most likely truck routes would traverse the populated Las Vegas Valley, he said.

    Links powered by inform.com


    Leave Your Comment 2 Reader Comments
    Terms & Conditions
    The following comments are provided by readers and are the sole responsiblity of the authors. The reviewjournal.com does not review comments before publication nor guarantee their accuracy. By publishing a comment here you agree to abide by the comment policy. If you see a comment that violates the policy, please notify the web editor.

    Some comments may not display immediately due to an automatic filter. These comments will be reviewed within 48 hours. Please do not submit a comment more than once.
    Current Word Count:

    John wrote on July 24, 2007 02:21 PM: This is the underlining reason why this city will never grow outward. One way or another Yucca WILL be the nuclear storage waste site for the entire country. There's no more feasible options and the government has already dumped billions in picking this site. This place is dead.


    Roger wrote on July 24, 2007 07:49 AM: Good! I hope those DOE idiots go bankrupt!